Capacitor Banks for Reactive Power Compensation
capacitor banks for reactive power compensation are shunt groups of capacitors that supply leading kVAR so lagging plant loads run closer to a target power factor. They fit a bus where VAR demand is steady or stepped, once harmonics have been checked, and they are the wrong object when the load needs continuous, bidirectional VARs.
A motor-heavy plant that “fixed” power factor with a bank can still blow fuses, ring with a drive, or watch voltage climb on a quiet shift. Capacitor bank sizing, detuning, placement, and the handoff to a static var generator are the decisions that follow.

Contents
- [What a shunt capacitor bank does on a plant bus](#what-a-shunt-capacitor-bank-does-on-a-plant-bus)
- [Capacitor bank sizing: kVAR from load and a PF target](#capacitor-bank-sizing-kvar-from-load-and-a-pf-target)
- [Fixed versus automatic stepped banks](#fixed-versus-automatic-stepped-banks)
- [Harmonic resonance, detuned banks, and light-load voltage rise](#harmonic-resonance-detuned-banks-and-light-load-voltage-rise)
- [When a capacitor bank is the wrong reactive-power object](#when-a-capacitor-bank-is-the-wrong-reactive-power-object)
- [Where the bank sits: upstream-only power-factor correction](#where-the-bank-sits-upstream-only-power-factor-correction)
- [Andeli LV SVG when the bank is the wrong object](#andeli-lv-svg-when-the-bank-is-the-wrong-object)
- [FAQ](#faq)
- [References](#references)
What a shunt capacitor bank does on a plant bus
A shunt capacitor bank is a set of capacitor units tied so they act together and inject leading reactive power beside inductive loads. In plain terms, it is the cabinet or rack that supplies the VARs motors would otherwise pull from the utility.
On medium-voltage systems, IEC 60871-1 is the general standard for capacitor units and banks used for power-factor correction above 1000 V. Low-voltage cans in a plant room sit outside that document, and nothing on an Andeli page turns that standard into a certificate.
Picture a bus full of induction motors at a pumping station or a machining line. Each motor draws active kilowatts and lagging reactive power; the shunt bank cancels part of that reactive current, line current falls, and the power factor meter moves toward the lagging target you set.
The same current drop frees transformer and cable capacity and, under heavy load, supports voltage. Output still follows voltage: when the bus sags, capacitive kvar falls with the square of voltage, so a bank sized at nominal voltage delivers less during the sag you hoped it would cover.

Capacitor bank sizing: kVAR from load and a PF target
Capacitor bank sizing starts from kilowatts you are actually running and from two power factor readings: today’s lagging value and the lagging value you want. Required kvar is Qc = P × (tan φ1 − tan φ2), with active power held constant.
Measure P and the present power factor at the same operating point you intend to correct. Convert each power factor to an angle, subtract the tangents, and multiply by kilowatts. That difference is the capacitive kvar to add, before you split it into steps the controller can switch.
Keep the target near 0.95 lagging rather than unity. A bank brought all the way to 1.0 has no inductive kvar left to absorb it when the big motors stop, and the meter can cross into a leading power factor on the light shift.
A worked shunt-compensation case moved an 800 kVA load from power factor 0.85 to 0.95 and required 217.8 kvar at the load bus. Treat that figure as one network’s arithmetic, then repeat the tangent method on your own kilowatt and power-factor readings before you release a purchase quantity.
| Input | What to record |
|---|---|
| Active power | Kilowatts at the operating point you intend to correct |
| Present power factor | Lagging value from the meter at that same point |
| Target power factor | Lagging target short of unity |
| Qc | P times the difference in tan φ |
Use the row for Qc only after the kilowatts and both power factors are from the same hour. Splitting the result into equal steps is a hardware choice in the next section, not a second formula.
Fixed versus automatic stepped banks
Use a fixed bank when VAR demand stays steady and is a modest share of the transformer. Use an automatic stepped bank when reactive demand moves with the process and you still want discrete capacitor sections rather than a continuous converter.
A common low-voltage heuristic puts the break at 15% of transformer kVA. At or below that share, a single fixed rack is the usual hardware; above it, a power-factor controller stages contactors so kvar tracks the shift.
Contactor-switched low-voltage banks are often preset to wait 20 to 60 seconds between steps. That pause keeps the contactors off a motor start, and it is also why a welder, crane, or fast compressor will still look uncorrected between steps.
A packaging line that runs the same motors all day can live with a fixed rack. A plant that drops to a night crew and leaves the day-shift capacitors online is the case for steps, or for taking sections off, before voltage starts to climb.
| Plant situation | Hardware that fits |
|---|---|
| Steady VAR, harmonics cleared, modest share of transformer capacity | Fixed shunt bank |
| VAR moves with shifts, still slow enough for contactors | Automatic stepped bank |
| Soft starter or VFD on the same bus | Detuned bank after a harmonic check |
| VARs swing faster than steps, or the bus must absorb VARs | Dynamic static var generator |
Read the last row as a stop, not as a larger capacitor order. If the bus needs VARs removed as well as added, more cans will not grow an absorbing mode.
Harmonic resonance, detuned banks, and light-load voltage rise
Harmonic resonance capacitor banks appear when untuned capacitors and the inductance of the supply land on a frequency the nonlinear loads already make. The cure is a detuned design or a smaller bank, not another plain step on the same bus.
Capacitors do not manufacture harmonics. Series resonance can drop the impedance at a harmonic and pull heavy current through the cans, and parallel resonance between a transformer and a power-factor bank can raise impedance until fuses open or the bank fails.
A 50 Hz literacy sketch, FR = 50 × √(short-circuit kVA / capacitor kvar), lands near 612 Hz for a 150 MVA short-circuit level and a 1000 kvar bank. Use that sketch to see how a large bank can sit near a drive harmonic, then commission a harmonic study before a plain bank is ordered.
A detuned reactor / detuned bank places a series reactor with the capacitors so the pair resonates below the harmonic the drives excite. On drive-rich buses that point is often set near the 4.7th, under the 5th harmonic, instead of leaving the cans untuned.
IEEE Fort Worth PES notes make the same split: shunt capacitors do not generate harmonics, but they open a path and can shift impedance until cans and fuses heat. Detuning the capacitor and reactor, and raising the current rating, are the mitigations those notes list.
From the field: Engineers keep asking what actually fails when a power-factor bank sits on the line side of a soft starter / VFD. Capacitor impedance falls as frequency rises, so the bank becomes a low-impedance sink for harmonic current, the cans heat, and resonance is in play if that frequency is already on the bus.
Effects of harmonics on capacitors walks through the series and parallel paths and treats a de-tuned filter as the hardware response. Pair that mechanism with the field complaint before you accept a plain bank beside soft starters.
Light-load overcompensation is the other quiet failure. If capacitive kvar left online is larger than the inductive kvar the motors are still drawing, power factor goes leading and line voltage rises.
An individual-motor illustration puts no-load magnetizing compensation near 12 kvar for a 50 HP motor. The 50 HP example warns that excess capacitor kvar can raise voltage enough to stress insulation, so a fixed bank sized for full load needs a way off when the shaft is idle.

When a capacitor bank is the wrong reactive-power object
If VARs swing faster than contactor steps, the bus must absorb VARs, or unbalance matters, a discrete bank is the wrong object. Specify a Static Var Generator (SVG), a converter that can supply or absorb reactive current under closed-loop control.
A spot welder, a crane, or a compressor that cycles every few seconds will finish the swing before a contactor step is allowed to close. The power-factor meter then shows the uncorrected load for most of the cycle, no matter how large the bank kvar is on the nameplate.
Absorbing VARs is the second miss. A capacitor section can only add leading kvar. When cable capacitance, a lightly loaded plant, or an oversized bank already pushes the meter leading, switching in more cans moves the wrong way.
Unbalance is the third miss. A shunt bank is a balanced capacitive block. It will not move current from a heavy phase to a light phase the way a converter running an unbalance mode can.
A discrete bank stays the slow step when voltage moves faster than contactors, and a converter is the continuous VAR source for that swing. Ordering another capacitor step does not remove the contactor delay.
Where the bank sits: upstream-only power-factor correction
Correction shows up only on the network toward the source from the connection point. Meters and feeders downstream of the bank still see the lagging motors.
Power quality basics put the same limit in placement language: a bank can sit at a load, upstream of a motor group, or at the service origin, and it corrects power factor upstream of that point only.
Put the bank where the meter you care about can see the VARs.
- At the motor terminals, that motor’s feeder is the stretch that improves.
- At a motor-control center, the group upstream of the rack improves, and individual starters downstream do not.
- At the service origin, the utility meter improves, and downstream departments keep their own reactive current.
A plant that paid for a main-incomer bank and then wondered why a subfeed meter still showed a lagging power factor was looking downstream of the cans. Move the kvar to the feeder the penalty meter actually reads, or add a second bank there.
Feeder placement research treats where the kvar lands, and how large the bank is, as a loss, voltage, and cost trade on a distribution feeder. Use that as a planning warning for multi-bus sites. It is not a performance number for any Andeli product.
Andeli LV SVG when the bank is the wrong object
Andeli does not list a capacitor-bank product. When the job needs dynamic VARs in both directions, the printed low-voltage static var generator is the in-family object, and the power-quality hub is where that line sits beside the rest of the power-quality range.
The Andeli low voltage static var generator is a converter placed in parallel through an inductor. It adjusts the converter voltage so the unit can absorb or supply reactive current, which is the dynamic behavior a stepped bank does not have.
Printed ratings are 50 Hz operation at 400 V, 690 V, and 800 V, each with a ±20% voltage window, a reactive-power compensation rate above 98%, and a full response time under 10 ms. Those figures are the page’s own listing for this low-voltage family.
Altitude is printed as under 2000 m, with derating above that height referred to IEC 3859-2, and ambient temperature is printed from -10 °C to 50 °C with derating above 40 °C. Stay with that printed frequency when you match a cabinet to the bus.
Printed low-voltage capacities include 30 kvar, 50 kvar, 75 kvar, 100 kvar, and 150 kvar on the 400 V family, 120 kvar on the 690 V family, and 140 kvar on the 800 V family. Operating modes on the page are reactive power and unbalance, on three-phase three-wire or four-wire systems.
A steady, harmonic-cleared, step-friendly bus can still use a capacitor bank from a supplier that actually builds one. Open the SVG specification when the bus swings faster than steps, needs VARs absorbed, or must deal with unbalance, and match the printed voltage and kvar family to that bus.

FAQ
What are capacitor banks for reactive power compensation?
They are grouped capacitor units in shunt with lagging loads. They inject leading kvar so the utility supplies less reactive current and the power factor moves toward a lagging target.
How do you size kvar for a capacitor bank?
Hold kilowatts constant, subtract the tangent of the target angle from the tangent of the present angle, and multiply by kilowatts. Keep the target lagging and short of unity so a quiet hour does not go leading.
When should you choose a fixed bank versus an automatic stepped bank?
Choose a fixed bank when VAR demand stays steady and is a modest share of transformer capacity. Choose automatic steps when the process turns reactive load up and down slowly enough for contactors.
What are the risks of capacitor banks with harmonics or soft starters?
Untuned cans on a drive or soft-starter bus can sink harmonic current and resonate with supply inductance, which heats the units and opens fuses. Detune with a series reactor, or leave the plain bank off that bus, after a harmonic check.
Can overcompensation raise voltage at light load?
Yes. Capacitive kvar left online after inductive kvar falls drives a leading power factor, and line voltage can rise enough to stress insulation. Take fixed sections off, or step them, when the motors idle.
When is a static var generator a better fit than a capacitor bank?
Use it when VAR demand moves faster than contactor steps, when the bus must absorb VARs, or when phase currents are badly unbalanced. A stepped bank only adds leading kvar in discrete chunks.
Does a capacitor bank correct power factor everywhere in the plant?
No. Correction appears upstream of the connection point only. A main-incomer bank does not fix a subfeed meter that still sits downstream of the cans.
Does Andeli sell a dedicated capacitor-bank product?
No. The power-quality range does not include a capacitor-bank product. The low-voltage static var generator is the converter to review when a bank is the wrong object.