How to Size Transformer kVA and %Z When Multiple Motors Start

2026-09-28

If several motors share one feeder transformer, size for running load plus the starting kVA of the motors that actually start together, then screen the voltage dip with that starting kVA against short-circuit kVA from nameplate percent impedance. Specifiers searching transformer sizing for multiple motors starting current inrush need that dual check—not a thermal FLA sum alone, and not a magnetizing-inrush fuse story. The sections below separate coincidence from stagger, walk through the dip screen and retained-voltage limits, and show which published oil-immersed catalog numbers can feed the study.

Illustrative timeline: motor starting current lasting seconds versus transformer magnetizing inrush lasting cycles

Contents

  • Running Load Is Not Starting Duty
  • Starting Current and Locked-Rotor kVA
  • Coincident Start vs Staggered Start
  • Percent Impedance, Short-Circuit kVA, and the Dip Screen
  • Voltage Limits: Bus, Contactors, and Motor Terminals
  • Soft Starters and VFDs vs Buying More kVA
  • When to Run a Motor-Starting Study
  • When Published Oil-Immersed Catalog Inputs Fit a Multi-Motor Starting Study
  • FAQ
  • References

Running Load Is Not Starting Duty

Steady-state distribution transformer kVA is necessary, but it is not enough when motors start. A unit that looks fine on a continuous-load sheet can still sag the bus during a direct-on-line start.

Plant MCC transformers are often sized from the sum of full-load amps plus growth. That thermal inventory covers heat and continuous duty. Starting current is mainly a short voltage problem: locked-rotor amps pull through transformer impedance for seconds while the motor accelerates.

A large pump that DOL-starts on a “sum of FLA” transformer is the classic miss. The sheet said the kVA was adequate; contactors and neighboring loads still saw an unacceptable motor starting voltage dip. Keep the running inventory, then add a separate start case.

Starting Current and Locked-Rotor kVA

Prefer nameplate locked-rotor amps or a NEMA code letter when you build starting kVA for transformer sizing for motor starting. Do not invent a single plant-wide multiplier.

Locked-rotor / starting current (LRA) is the current drawn while the rotor is stalled or nearly stalled at full voltage—the amp surge while the motor is still winding up. Across-the-line (DOL) cage induction motors commonly draw about 6–8× full-load amps; IEC Design N and H ranges sit in a similar band, but the nameplate wins.

For three-phase motors, starting kVA is √3 × V × LRA / 1000. When LRA is missing, a NEMA code letter supplies locked-rotor kVA per horsepower (code bands A–V). That locked rotor kVA is the transient demand you compare with transformer short-circuit kVA in the dip screen.

Inrush (motor vs magnetizing) must stay separated: magnetizing inrush is transformer core saturation for a few cycles at energization, while motor starting current lasts seconds. Mixing those two species leads people to fuse curves when they needed a starting-voltage check.

Coincident Start vs Staggered Start

Default screen for several motors is others running plus the largest motor starting, unless controls prove coincidence. Do not add every motor’s locked-rotor kVA unless those motors actually start together.

Simultaneous vs staggered start is the multi-motor decision. Staggered or sequential start means interlocks or a PLC fire one starter at a time so only one LRA event overlaps the running load.

Coincident start means two or more LRA events overlap—by design or by interlock failure. Voltage dip / sag during that overlap is what the transformer screen is for.

One-line diagram comparing simultaneous motor starts versus staggered starts on one transformer

Three conveyors on one MCC make the difference concrete. With a proven stagger, size for two running plus one starting. If all three can slam on together, practitioners often keep combined full-load loading near about 60–65% of transformer FLA as a conservative thumb rule—not factory data from any one brand.

Write the start philosophy into the control narrative before you pick the next kVA step. Coincidence is a controls fact, not a catalog claim.

Percent Impedance, Short-Circuit kVA, and the Dip Screen

Approximate percent voltage dip from starting kVA versus transformer short-circuit kVA, using nameplate %Z on an infinite-bus screen. Larger kVA or lower percent impedance cuts the dip but raises available fault current.

Percent impedance (%Z / uk% / impedance voltage) sets how stiff the transformer looks during a start. Approximate short-circuit kVA at the secondary is rated kVA × 100 / %Z when you treat the utility as infinite. A common screen is % dip ≈ Starting kVA / (Starting kVA + SC kVA) × 100.

A worked teaching case uses a 7500 kVA transformer at 8% impedance: SC kVA is 93,750 kVA. With a 2000 hp Code J motor whose starting kVA is 15,200 kVA, the screened dip is 13.95% on that infinite-bus model. Add utility source strength and feeder impedance when those numbers exist; the screen alone is not a full study.

The same motors on a smaller kVA band or a higher published %Z look softer. A next size up, or a lower published impedance band, reduces dip—and raises fault duty that switchgear must still clear.

Voltage Limits: Bus, Contactors, and Motor Terminals

Practice clusters around about 90% bus caution, about 85% for contactor hold-in, and about 80% at motor terminals—project specs still win. There is no single code number that closes every plant.

During a start, retained voltage falls at the bus or motor terminals. Contactor dropout is often the first real-world limit: coils that chatter or drop out kill the start even if the motor could still accelerate.

Illustrative retained-voltage checkpoints for bus caution, contactor hold-in, and motor terminals during motor starting

From the field: Plants have seen neighboring compressor contactors drop out when a large mill DOL-starts on a shared bus—the pain is not only “will the starting motor turn,” but whether other loads stay online. Field discussions also split bus caution near 90%, contactor hold-in near 85%, and motor-terminal success bands near 80%, with utility flicker limits sometimes tighter at the PCC.

Keep the screen conservative and escalate to a study when motor data sheets are thin, rather than guessing a softer limit.

Soft Starters and VFDs vs Buying More kVA

Reduced-voltage starters and VFDs can cut line starting multiples enough to keep an existing transformer when torque still starts the load. Buying the next kVA step is not the only lever.

Start method Typical line starting-current multiple What it changes for the transformer
DOL / across-the-line About 6–8× FLA Highest line starting kVA; stiffest dip case for a DOL / across-the-line starter
Wye–delta About 2.0–2.7× FLA Lower line current; torque falls with voltage
Autotransformer 80% / 65% About 3.8–5.1× / 2.5–3.4× FLA Reduced voltage steps; still a line-current event
Soft starter About 2–4× FLA Ramp settings must still produce breakaway torque
VFD About 1.0–1.5× FLA Lowest classic inrush on the line when applied correctly

Order-of-magnitude soft starter / VFD ranges are settings-dependent. A published case on a large pump with a 100 MVA source shows DOL near 15% drop, reduced-voltage soft start near 8%, and VFD under 5% for that network—useful as method literacy, not as your plant’s result.

When to Run a Motor-Starting Study

When the largest motor is a large fraction of transformer base kVA, or limits and source data are thin, commission a motor-starting study. Thumb-rule screens stop being enough.

Plant distribution transformer feeding multiple motors during starting on an outdoor pad near an MCC building

An IEEE 3002.7 study trigger used in plant studies is to run a formal starting study when motor horsepower is about 30% or more of the supply transformer base kVA. Generator-fed plants often use a tighter share of generator kVA. Missing LRA, unknown utility short-circuit strength, or frequent starts push the same way.

The study is not a product brochure step. It is the escalation when coincidence, %Z, and retained-voltage bands cannot be closed with a simple screen.

When Published Oil-Immersed Catalog Inputs Fit a Multi-Motor Starting Study

Use published kVA bands, HV/LV, Dyn11, and impedance voltage 4.0% / 4.5% / 5.0% as study inputs—not as a start-success certificate. Andeli’s 6–10 kV oil-immersed distribution transformer tables supply those catalog numbers for an oil-immersed 6–10 kV transformer on the transformer hub.

Andeli 6–10 kV oil-immersed distribution transformer product photo

Published S11 distribution rows step HV at 11 / 10.5 / 10 / 6.3 / 6 kV to LV 0.4 kV, with typical Dyn11 (also Yzn11 / Yyn0). Impedance voltage is 4.0% for 30–500 kVA, 4.5% for 630–1600 kVA, and 5.0% for 2000–2500 kVA under GB 1094 / GB/T 6451 language on the product tables.

Transformer kVA band (published) Published %Z Approximate SC kVA (kVA × 100 / %Z) Example starting kVA (illustrative) Screened % dip (illustrative)
500 kVA 4.0% 12,500 kVA 2,500 kVA 16.7%
1000 kVA 4.5% 22,222 kVA 2,500 kVA 10.1%
2000 kVA 5.0% 40,000 kVA 2,500 kVA 5.9%

Those worksheet columns are illustrative inputs for the infinite-bus screen. They do not prove a motor train will start on your bus, and they do not invent factory LRA multipliers or UL / IEEE / NEC / DOE listings for the series.

If your project needs documented US listings or factory starting-duty curves, those claims are outside the published tables—escalate to a formal starting study with the numbers you do have.

FAQ

If several motors share one transformer, do I add every motor’s locked-rotor kVA?

Only if those motors start together. The usual screen is running load of the others plus starting kVA of the largest motor, with coincidence proven by controls when you need a heavier case.

What voltage dip is “acceptable” when the largest motor starts?

Common engineering bands sit near 90% retained bus voltage as caution, near 85% for contactor hold-in, and near 80% at motor terminals. Project specifications and motor data sheets override any single rule of thumb.

How is transformer percent impedance used in a starting-current check?

Nameplate %Z estimates transformer short-circuit kVA as kVA × 100 / %Z on an infinite-bus model. Screen % dip ≈ starting kVA / (starting kVA + SC kVA) × 100, then add source and feeder data when available.

Is transformer magnetizing inrush the same as motor starting current?

No. Magnetizing inrush is a few-cycle core-saturation spike when the transformer itself is energized. Motor starting current is locked-rotor / acceleration current lasting seconds.

Does NEC 430’s extra 25% of the largest motor size the transformer kVA?

No. NEC 430 OCPD and feeder rules size protection and conductors; they are not a transformer kVA design method for starting voltage. Keep breaker sizing and transformer dip sizing as separate tasks.

When should we leave rules of thumb and run a motor-starting study?

When the largest motor is a large slice of transformer base kVA—IEEE-cited practice often flags about 30% HP relative to transformer kVA—or when coincidence, utility strength, or retained-voltage limits cannot be closed with a screen.

Can a soft starter or VFD avoid buying the next transformer size?

Often, if the reduced line starting multiple still produces enough torque for the driven load. Soft starters commonly land near 2–4× FLA and VFDs near 1–1.5× FLA on the line, versus about 6–8× for DOL.

What published 6–10 kV oil-immersed numbers are usable as study inputs?

Published capacity bands, HV/LV (including 0.4 kV LV), Dyn11, and impedance voltage 4.0% / 4.5% / 5.0% by kVA band on the Andeli oil-immersed series tables. Do not invent factory motor-inrush multipliers from those rows.

References

  1. Sizing Transformers with Large Motor Loads — Electrical Knowhow — dip formula, SC kVA from %Z, multi-motor largest-start practice.
  2. Sizing Transformers with Large Motor Loads — CESEEPS — SC kVA in transformer sizing; shared-bus dropout pattern.
  3. Motor Starting Studies and IEEE Criteria — IJSDR 2405183 — IEEE 3002.7-cited study trigger when motor HP is a large fraction of transformer kVA.
  4. Motor inrush current — r/electricians discussion — community language separating first-cycle inrush from multi-second locked-rotor / ramp current.