Isolate first: a hold-point path for medium voltage switchgear testing
Medium voltage switchgear testing is a lineup SAT: isolate the assembly, prove the local bus dead, hold insulation resistance before CT/VT work, then run contact resistance and injection, and apply hi-pot last at the OEM voltage.
Isolation order, the SAT hold-point sequence, the insulation-resistance gate, and the gap between nameplate withstand figures and field volts are the four decisions that keep a remote ground or a copied blog voltage from becoming the test plan.

Prove the bus dead before any test set is connected
Isolation is unfinished when a remote ground truck is already on the feed; prove the local bus dead, apply grounds at the gear, and still treat the lineup as live.
A crew can ground the incoming feed in another room and still walk up to a live bus in the cubicle they opened. Open the feeder, get a visible break, earth the work zone, lock it out, then prove dead at the local bus before any leads land on bushings or bus bars.
From the field: After a ground truck is on the feed in a totally different location, r/IBEW crews still test the bus of the gear they are working on and treat everything as live, including 40 cal arc-flash suits. A commenter flagged the written order that listed grounding first and testing second.
Mechanical hold points ride with that prove-dead step. Charge the vacuum circuit breaker spring by hand, rack between test and service, and try the earthing-switch interlocks: earthing ON should keep the truck in test, and a racked-in closed breaker should block earth-switch close and compartment doors.
Withdrawable voltage transformer trays have to roll without fighting the wheels or the primary contacts. A tray that hangs up is an undesired live-bus condition, not a cosmetic complaint.

What the metal-enclosed lineup actually is
Test the bus, the breaker, the instrument transformers, and the cable interface as separate insulation systems.
Medium-voltage switchgear in this article is a prefabricated metal-enclosed assembly: main bus, a withdrawable or fixed vacuum circuit breaker, current transformer and voltage transformer sets, earth and disconnect switches, and the protection wiring that sits on those secondaries. One megger reading across a closed door does not stand in for that stack.
A current transformer secondary that is left open while primary current is possible is its own hazard. A voltage transformer left hung on a bus megger is a damaged VT waiting to happen.
Cable terminations and surge arresters belong on their own isolation list before anyone stresses the bus. For CT versus VT connection and secondary hazards, see Andeli’s current transformer versus voltage transformer selection guide.
Andeli groups indoor armored withdrawable cubicles with its other indoor MV gear on the Medium and Highty Voltage hub and the metal-clad AC enclosed switchgear family page. KYN28A-12 with a VS1 or Vd4 truck is the lineup this procedure is about.

A medium voltage switchgear testing procedure with SAT hold points
A usable medium voltage switchgear testing procedure follows a published site acceptance test SAT procedure: mechanical and visual first, then CT/VT, then breaker insulation resistance, contact resistance, and timing, then secondary injection, then bus contact resistance and primary injection, then functional interlocks, then hi-pot last.
That order is the SAT map after erection and inter-panel wiring, and before plant cables land. Nameplates have to match the approved drawings; a mismatch is a stop, not a punch-list item for later.
| Hold point | What you prove | Stop if |
|---|---|---|
| Mechanical / visual | Racking, interlocks, torque, nameplate match | Truck binds, interlock defeated, drawing mismatch |
| CT / VT | Polarity, ratio, winding IR; VT isolated from the bus megger | Open CT secondary, VT left on the bus, ratio off drawing |
| Breaker IR / CRM / timing | Dry insulation, tight closed path, mechanism times | Failed IR, wild phase spread, no OEM/FAT baseline |
| Secondary injection | Relay, meter, trip-circuit, and TCS behavior | Relay fails to trip the vacuum circuit breaker |
| Bus CRM / primary injection | Joint tightness and CT circuit with current on the primary | Open joint, CT wiring error between feeders |
| Functional interlocks | Earth switch, shutters, door and keylock logic | Interlock can be forced |
| Hi-pot last | Dielectric after a passed IR and VT isolation | IR failed, VT still connected, voltage taken from a blog table |
Secondary injection is the relay and meter proof. Primary injection is the CT-circuit proof with current on the primary, often about 100 A between feeders on that published SAT.
Insulation resistance is the hold point before any hi-pot
Do not hi-pot a lineup that has not passed insulation resistance; isolate voltage transformers, arresters, and relay inputs first, and short current transformer secondaries.
Insulation resistance — the Megger — is the first electrical gate. Results are comparative, and they tell you whether the insulation is dry enough to stress.
They do not prove power-frequency withstand.
A field IR table for 3.6–12 kV class gear commonly uses 2,500–5,000 V DC. Leave a voltage transformer on a 5,000 V bus megger and you can damage the VT; VT primary-to-ground is often run at 1,000 V DC. Forum Electrical’s SAT CT/VT IR set uses 5 kV primary-earth, 2.5 kV primary-secondary, and 1 kV secondary-earth.
Pull auxiliary devices such as PTs and arresters before the bus shot. Test the breaker open and closed, and test each bus phase to ground with the other phases grounded.
Isolate spring-charging motors and solid-state devices when you megger control wiring.

Contact resistance, timing, and the current path
Use a high-current ductor on closed joints, compare phases and the OEM or factory baseline, and add timing where the breaker class warrants it.
Contact resistance is the closed-path check: bushing to bushing on a closed vacuum circuit breaker, and joint to joint on the bus. The repeated field current is 100 A DC or the breaker rating. Many manufacturers will not honor a warranty argument built on a 10 A DLRO.
If the specification invokes NETA, adjacent phases should stay within 50 percent of each other. IEEE C37.09 is cited in field notes as a cap: contact resistance should not exceed factory values by more than 200 percent. An EEP 15 kV-class example lands around 200–250 µΩ; treat that as an illustration, then compare your phases to each other and to the OEM sheet.
Timing and travel show up more often on 34 kV and above. An EEP close-time example runs 31.4 / 30.2 / 31.8 ms, with phase-to-phase spread held to 2 ms for most breakers. Trip the vacuum circuit breaker through the protective relay, not only the local close/open switch.
Hi-pot last, and only at OEM volts
Prefer AC withstand for AC assemblies; run the high-potential test last after insulation resistance and voltage-transformer isolation; take vacuum-bottle volts only from the OEM manual.
DC hi-pot is a fallback on AC switchgear, not the matching stress. Maintenance AC values in one widely copied table are 75 percent of factory proof. That table’s 13.8 kV example lists 36 kV AC factory and 27 kV AC maintenance, with a one-minute DC figure of 38.2 kV.
A China-market how-to quotes 42 kV for one minute on a 10 kV assembly.
An independent IEC-style guide lists 28 kV power-frequency and 60/75 kV BIL at 12 kV. One published SAT holds 24 kV for 60 seconds with VTs racked out.
Andeli’s KYN28A-12 12 kV column prints 42 kV and 75 kV as nameplate ratings.
Vacuum bottles add X-ray risk when substantial voltage sits across open contacts. Use AC if the OEM says AC.
A utility thread cites about 37 kV for a 15 kV breaker bottle, then tells you to check the maintenance manual.
VLF belongs on connected cable. It is the wrong substitute for assembly insulation resistance and hi-pot.
Type tests, SAT, and NETA are different jobs
Factory type tests prove a design; SAT repeats a subset on the erected lineup; NETA ATS applies only when the specification invokes it.
IEC 62271-200 is the current international standard for AC metal-enclosed switchgear from above 1 kV to 52 kV, indoor and outdoor, at service frequencies up to 60 Hz.
Its laboratory type-test list — dielectric, temperature rise, short-time withstand, mechanical endurance — is once per design. Routine tests ride with every serial unit, and site-after-erection work is closer to that routine subset than to an IAC film.
Andeli’s published KYN28A-12 standards line is GB/T3906, GB/T11022, and IEC 60298. Industry SAT language now points at IEC 62271-200.
IEEE C37 is the US switchgear and breaker-test family, including C37.09 contact-resistance language. NETA ATS is the US acceptance spec for new equipment before service when the project writes it in.
Power-factor on MV gear is often optional under that spec; overpotential is mandatory only if NETA is the invoked document. Andeli pages do not claim NETA or IEEE type-test credentials.
KYN28A nameplate ratings are context, not SAT voltages
Printed withstand figures on KYN28A-12 are nameplate design ratings, not the volts you apply on site.
The KYN28A-12 parameter table lists GB/T3906, GB/T11022, and IEC 60298, and the 12 kV column shows 42 kV one-minute power-frequency and 75 kV BIL.
KYN28A-12 withdrawable metal-enclosed switchgear is the indoor armored withdrawable lineup a 3.6/7.2/12 kV commissioning crew is testing: 50 Hz, rated current options 630–4000 A, 4 s short-time 20–50 kA, enclosure IP4X and compartment IP2X, ambient −25 °C to +40 °C below 1000 m. Associated breakers on that table are Vd4 and VS1-12 kV, with the VS1 row also listing 42 kV one-minute power-frequency and 75 kV BIL.
Read those numbers as rating context, then pull the IOM for the volts you will actually apply. Andeli does not publish factory SAT voltages for KYN28A-12.
XGN15-12 is a different 12 kV architecture: SF6 load-break RMU, 630 A, IP3X, 25 kA / 2 s, published 42 kV phase-earth and 48 kV across the open gap, BIL 75/85 kV. SF6 density checks belong there. They do not migrate onto a KYN28A air-insulated withdrawable SAT.
More MV devices sit on the same Medium and Highty Voltage hub. If the need is ring-network SF6, stop here and change families. If the need is indoor withdrawable metal-clad in the 3.6/7.2/12 kV class, the KYN28A-12 table is the nameplate you already learned how to read.
| Figure | Where it came from | What you may do with it |
|---|---|---|
| KYN28A-12 12 kV column: 42 kV / 1 min PF, 75 kV BIL | Andeli product table | Nameplate / design rating only |
| 10 kV assembly example: 42 kV / 1 min | Generic China-market how-to | Compare to the OEM IOM |
| 12 kV PF 28 kV; BIL 60/75 kV | Independent IEC-style field guide | Proves tables disagree; use the OEM IOM |
| 13.8 kV: 36 kV factory AC / 27 kV maintenance AC | EEP maintenance table | US-class example; still defer to OEM |
| 24 kV / 60 s, VTs racked out | One published SAT write-up | That author’s example only |

FAQ
Why run insulation resistance before a hi-pot?
Insulation resistance is the dry-enough gate. A failed or skipped megger is how a hi-pot becomes a flashover on dirty insulation.
What is the CRM / contact-resistance test on a breaker or bus?
It is a high-current micro-ohmmeter shot on a closed path, usually 100 A DC, then a phase-to-phase and OEM-baseline compare.
How should CTs and VTs be handled during lineup tests?
Prove CT and VT ratio, polarity, and winding IR first. Short CT secondaries. Rack or isolate VTs before any bus megger or hi-pot.
Do OEM limits override generic hi-pot voltage tables?
Yes. When a 42 kV how-to, a 28 kV guide row, and a 42/75 kV nameplate disagree, take the volts from the OEM IOM for that serial lineup.
Is power-factor testing mandatory at SAT?
Only if the owner or the invoked spec adds it. Under NETA-style acceptance language, overpotential is the usual mandatory item and power factor is optional.
Why do vacuum-bottle hi-pots mention X-rays?
Substantial voltage across open vacuum contacts can produce X-rays. Use the OEM bottle voltage and the AC-or-DC method the manual names.
What standards apply to medium voltage switchgear testing?
Industry metal-enclosed language now points to IEC 62271-200. US field specs may invoke IEEE C37 and NETA ATS. Andeli’s published KYN28A-12 line remains GB/T3906, GB/T11022, and IEC 60298.
Does Andeli publish factory SAT numbers for KYN28A?
No. The KYN28A-12 parameter table publishes nameplate ratings. SAT voltages come from the OEM IOM for that serial lineup.