What Counts as Medium Voltage Switchgear Installation Indoors
Medium voltage switchgear installation is complete when the switch room is finished and usable, shipping sections are set true and bolted, main bus and MV/control cables land per the drawings, and mechanical or key interlocks still enforce the intended sequence. For indoor medium-voltage switchgear, a finished mechanical lineup differs from a type-test certificate and from a finished site acceptance test. The sections below cover room readiness, shipping-section erection, bus and cable landings, interlock checks, and the handoff point where testing work begins.

Contents
- What “installed” means for indoor MV metal-enclosed switchgear
- Switch room, foundation, conduits, and IAC exhaust consequences
- Shipping sections: set, level, bolt, then land the main bus
- Bus joints, cable terminations, and shipping-split control landings
- Interlocks, earthing switches, and withdrawable truck checks
- Where installation stops—and why this is not a testing procedure
- When an indoor AIS withdrawable lineup such as KYN28A-12 fits
- FAQ
- References
What “installed” means for indoor MV metal-enclosed switchgear
Installed means as-built mechanical and interface completion per the order drawings and the lineup instruction manual. It differs from a passed type-test certificate and from a finished site acceptance test. Indoor metal-enclosed assemblies for AC service above 1 kV up to 52 kV sit in the IEC 62271-200 family scope for prefabricated metal-enclosed switchgear and controlgear.
North American metal-clad language is different.
IEEE C37.20.2 describes metal-clad construction with drawout circuit breakers and grounded metal barriers between compartments. GB/IEC armored withdrawable air-insulated (AIS) lineups use metal-enclosed / armored wording instead. Treat those vocabularies as parallel construction languages, not interchangeable nameplate claims.
| Construction language | What it usually names | What installation work still has to prove on site |
|---|---|---|
| IEC metal-enclosed (62271-200 family; legacy IEC 60298 name still appears on some product pages) | Prefabricated indoor/outdoor metal-enclosed assemblies, including air-insulated compartments | Room finish, shipping joints, landings, and interlocks match drawings |
| IEEE metal-clad (C37.20.2) | Drawout breaker, grounded metal barriers, compartmented MV switchgear | Same field mechanical interfaces—definition language does not waive erection quality |
| Loss of service continuity (LSC) | How much of the assembly can stay operable when a compartment is opened | Operating intent on drawings; civil-room certificate is out of scope |
| Internal arc classification (IAC) | Which faces (F/L/R), accessibility, current, and time were classified in a type test | Exhaust path and room pressure remain a civil/design check |
Published erection guidance for metal-enclosed lineups repeats a practical rule: equipment reaches its published ratings only after it is installed to the as-built drawings and the room’s environmental controls are in place. That is why indoor metal-enclosed switchgear installation literacy starts with the switchgear room / foundation and the joints before any test report is waved at the door.
Switch room, foundation, conduits, and IAC exhaust consequences
The room must be finished, dry, lockable, ventilated, and clear of storage before the first cubicle is set. Cable ducts or conduits should be complete enough that crews are not cutting floors after the lineup is placed. Lighting and temporary site power should already support safe work.

On US jobs where OSHA applies, 29 CFR 1910.303 requires usable working space, unblocked ventilation openings, and installation that follows the equipment instructions. Working space stays clear of stored crates and materials. Minimum working-space width is 762 mm (30 in.) or the equipment width, whichever is greater, with doors able to open to 90°.
Foundation and sill tolerances belong to the order drawings and the lineup’s own instruction manual. Typical erection practice calls for level, straight channel or frame support so withdrawable trucks and bus joints are not twisted later. Pad-flatness and aisle numbers stay with that lineup’s manual rather than being copied from another OEM family.
Loss of service continuity (LSC) is an IEC category that describes how much of the assembly stays operable when a compartment is opened. Internal arc classification (IAC) is a type-test string about which enclosure faces were classified. Neither label by itself proves that the civil room can take hot-gas reflection from the ceiling or a designed pressure-relief path.
Important: IAC face letters (F/L/R) classify tested switchgear faces. They do not verify that the room behind the lineup can withstand exhaust pressure. Room relief and ceiling reflection remain a civil/design check alongside any type-test plate string — source: Electrical Engineering Portal installation guidelines on IAC faces versus room pressure.
When enclosure ingress protection matters for ambient planning, quote only published model values. For Andeli’s KYN28A-12 indoor armored withdrawable lineup, the product page states enclosure IP4X and compartment IP2X, with ambient -25 °C to +40 °C and altitude below 1000 m unless negotiated.
Shipping sections: set, level, bolt, then land the main bus
Align and bolt shipping sections true—often center-out on long boards—before landing through-bus joints so rails and bars are not stressed. A shipping section (transport unit / shipping split) is the factory-shipped block of one or more cubicles that arrives on the truck and must be fastened into one lineup before through-bus work.
A practical medium voltage switchgear installation procedure for multi-section boards follows this order:
- Confirm the room gate above is closed.
- Set the first shipping section—commonly the center section on long lineups—so conduit and rail errors do not accumulate from one end.
- Bring adjacent sections into plumb and level on the runner rails; shim only as the lineup manual allows.
- Bolt section frames together before anchoring every sill bolt or installing the horizontal main bus.
- Only then land and torque the through-bus joints to the drawing and torque table for that lineup.
Misalignment shows up later as stress on interpanel busbars, earth bars, and withdrawable-truck rails. Crews that “set everything, then force the bus” pay for that sequence in bent joints and sticky trucks. Keep floor openings, conduit stubs, and truck-aisle elevation consistent with the drawings before the lineup grows past the point of easy correction.
Bus joints, cable terminations, and shipping-split control landings
Bus splices, cable-compartment terminations, and control wiring across shipping splits are three different interfaces. Cable hi-pot or VLF withstand work stays with the testing plan rather than the erection walk-down.

| Landing type | What is being closed | Reader decision |
|---|---|---|
| Main bus joint | Through-going phase conductors between bolted shipping sections | Cubicles true and bolted first; then land and torque per the lineup torque data |
| MV cable termination / cable compartment landing | Incoming or outgoing MV cable ends in the cable compartment | Termination kit and stress control per cable and drawing—not the same fastener set as a bus splice |
| Shipping-split control wiring | Secondary and control circuits that jump factory shipping breaks | Continuity and terminal marks across splits before energizing control power |
A main bus joint is the copper or aluminum bar connection that ties adjacent panels together after the cubicles are true.
A cable termination is where feeder cables bolt into the cable compartment.
Plant teams replacing older 15 kV gear often debate whether to test existing feeders before or after new terminations. Keep that debate with the testing plan. On the install walk-down, confirm the cable is landed, supported, and phase-marked per drawings.
Control wiring between shipping splits is easy to miss because the primary bus looks finished. Owner checklists commonly call out manufacturer control wiring across splits, ground-bus bonds, and unobstructed vents as mechanical close-out items. Current transformer secondary leads that cross a shipping break belong on that same punch list as landing interfaces.
Interlocks, earthing switches, and withdrawable truck checks
Earthing switches and key interlocks enforce sequence; lockout and proving de-energized remain separate site controls, and cover/earth interlocking gaps belong on the punch list. After the lineup is set, the mechanical story is incomplete until a withdrawable circuit breaker truck still racks cleanly and the mechanical / key interlock set still matches the drawings.
An earthing switch (grounding switch) ties bus or cable to earth so workers are not relying only on an open breaker. Community explanations of medium-voltage symbols treat the earth switch as a further protection layer above opening and padlocking a breaker. Trapped-key interlocking forces a defined operating order—for example, preventing access until the earth path is applied.
Field objections often appear during commissioning punch lists: a rear cover that opens without interlocking to the earth switch is a sequence defect that belongs on the punch list before energization. Walk the key board against the interlocking drawing. Confirm CPT or VT fuse access, shutter linkage, and truck positions still agree with the as-built scheme after shipping sections were bolted.

Wikipedia’s overview of switchgear construction ties metal-clad/metal-enclosed barriers, mechanical interlocks, and indoor internal-arc type tests together as construction and safety concepts. On site, interlocks force sequence while proving de-energized stays a separate step.
Where installation stops—and why this is not a testing procedure
Once room, joints, landings, and interlocks match drawings, mechanical installation is done. Insulation withstand, site acceptance testing, and going-alive checklists belong to a separate work package.
| Install-complete check | What that check does not prove |
|---|---|
| Switch room finished, dry, lockable, ventilated; working space clear | That IAC letters certify room exhaust pressure |
| Shipping sections level, bolted, and true before main-bus landing | That type-test ratings are “re-earned” by bolting alone |
| Main bus, MV cable terminations, and shipping-split control wiring closed per drawings | That cable or bus hi-pot / VLF results are acceptable |
| Earthing switches, key interlocks, and truck racking match drawings | That lockout/tagout or proving de-energized can be skipped |
| Environmental controls running as required by the lineup manual | That SAT or NETA-style procedures are complete |
The boundary matters because many OEM chapters and erection articles collapse installation into hi-pot and energization. This page stops at wiring and installation literacy for the indoor lineup. When the walk-down above is complete, hand the package to the testing procedure owned by the project—not by reusing this install checklist as a SAT script.
When an indoor AIS withdrawable lineup such as KYN28A-12 fits
Use published KYN28A-12 scope when the job is indoor armored withdrawable AIS. Treat UL or IEEE listing claims as out of scope for this SKU page. For cluster context under Andeli’s medium and high voltage hub, the live indoor armored withdrawable metal-enclosed model is the KYN28A-12 indoor armored withdrawable switchgear.

Published options for this indoor armored withdrawable lineup are summarized below.
KYN28A-12(Z)(GZS1) is published for three-phase AC 50 Hz receive, distribute, control, protect, and monitor duty. Named standards on the product page are GB/T3906, GB/T11022, and IEC 60298.
Rated voltage options are 3.6 / 7.2 / 12 kV, with paired one-minute power-frequency withstand 24 / 32 / 42 kV and BIL 40 / 60 / 75 kV. Published current options include 630–4000 A, with 4 s short-time withstand options 20–50 kA.
Enclosure IP4X and compartment IP2X apply as published, with ambient -25 °C to +40 °C and altitude below 1000 m unless negotiated. Associated breaker families named on the page include Vd4 and VS1-12 kV.
That scope fits withdrawable switchgear installation indoors when the project is specifying GB/IEC armored AIS cubicles with withdrawable vacuum breakers. Choose a different construction class when the buyer needs IEEE C37.20.2 or UL listing text the product page does not publish, a 60 Hz nameplate as if it were listed, GIS compact-indoor construction, or a pad-mounted transformer specification. Open the product page for published options, then return to the project order drawings and lineup manual for erection tolerances.
FAQ
What has to be finished in the switchgear room before the first cubicle is set?
The room should be lockable, dry, lit, and ventilated, with cable routes or conduits complete enough that floors are not reworked after cubicles land. Working space must stay clear of storage, and any pressure-relief or exhaust path required by the design should already be understood by the civil package.
Why do long lineups start at the center shipping section?
Starting near the center and working toward both ends limits cumulative conduit and rail error along a long board. End-to-end stacking can walk the lineup off the stub-ups and twist truck rails before the main bus is even landed.
When should main-bus bolts be torqued versus left loose?
Typical metal-enclosed erection practice aligns and bolts shipping sections first, then lands the through-bus. Follow the lineup torque table: joints are often seated loose for fit, then torqued only after sections are true. Another brand’s torque numbers stay with that brand’s manual.
How is a cable termination different from a shipping-split bus joint?
A bus joint ties adjacent cubicles’ through-going phase bars after the frames are bolted. A cable termination lands an incoming or outgoing MV feeder in the cable compartment with the correct stress-control kit. Closing one interface does not close the other.
Do earthing switches and key interlocks replace lockout?
No. They enforce a designed operating sequence and add an earth path when applied. Workers still need a proven de-energized state and the site’s lockout procedure before entering compartments.
Does a completed installation prove type-test ratings or replace SAT?
No. Mechanical completion shows the room, joints, landings, and interlocks match drawings. Type-test ratings remain with the type-test evidence for that design, and site acceptance or insulation testing remains a separate package.
Can KYN28A-12 be specified as IEEE C37.20.2 / UL listed from the Andeli page?
No. The published KYN28A-12 page names GB/T3906, GB/T11022, and IEC 60298.
It does not publish UL, IEEE C37.20.2, DOE, or NETA installation listings. Use IEEE C37.20.2 only as North American definition language when comparing construction classes.
What do IAC letters mean for the room behind the lineup?
IAC letters describe which switchgear faces were classified in an internal-arc type test, along with accessibility and test values on the type plate. They do not by themselves prove the civil room can take exhaust or hot-gas reflection; that remains a room-design check.
References
- IEC Webstore — IEC 62271-200:2021 catalog abstract (metal-enclosed switchgear and controlgear scope).
- OSHA — 29 CFR 1910.303 (electrical installation and working space).
- IEEE SA — IEEE C37.20.2-2025 catalog abstract (metal-clad switchgear).
- Electrical Engineering Portal — Installation guidelines for MV metal-enclosed switchgear (IEC 62271-200 LSC/IAC literacy).
- Electrical Engineering Portal — Erection procedures for medium voltage switchgear.
- Wikipedia — Switchgear (metal-clad / interlocking / IAC overview).
- Electronics Stack Exchange — Earth switch / switch-disconnector symbol discussion.