The commissioning of a new or recently overhauled transformer​ is a critical phase in power system operation. Before being officially energized, these units are required to undergo a series of switching surge tests, also known as impulse or inrush current tests. This crucial procedure serves three primary purposes, ensuring the safety, reliability, and longevity of the equipment, whether it's a compact dry transformer​ for indoor use or a high-capacity oil transformer​ for substations.

1. Assessing Insulation Strength and Detecting Defects

When a transformer is energized, especially under no-load conditions, it can generate high-magnitude switching surges or transient overvoltages. The severity depends on the grounding system:
  • In ungrounded or resonant-grounded systems, overvoltages can reach 4–4.5 times the phase voltage.
  • In solidly grounded systems, they can still reach up to 3 times the phase voltage.
The abrupt application of full line voltage during a surge test subjects the transformer​ insulation to severe electrical strain. This test effectively "stress-tests" the insulation system—including windings, bushings, and associated connections—to uncover any hidden weaknesses, contamination, or manufacturing defects. A failure during this controlled test prevents a catastrophic in-service failure, protecting the entire network. This is a vital quality check for all types of transformer, from distribution units to critical 35kv power transformers.

2. Verifying Differential Protection Stability and Settings

Energizing an unloaded transformer produces a phenomenon known as magnetizing inrush current. This transient current can reach 6 to 8 times the transformer's rated current. Although it decays rapidly initially, it can persist for several seconds in large units.
This inrush current can mimic the signature of an internal fault, potentially causing the transformer's primary differential protection relay to operate incorrectly (mal-trip), blocking a successful energization. The switching surge test provides a real-world scenario to:
  • Verify​ the correct wiring and stability of the differential relay.
  • Evaluate​ the effectiveness of harmonic restraint or other inrush discrimination algorithms.
  • Validate​ that the protection settings are appropriate to restrain during inrush but operate swiftly during actual faults.
This ensures that the protection system for a 35kv power transformer​ or any other class is both secure and reliable from day one.

3. Testing Mechanical Withstand Capability

The high magnetizing inrush current is not just an electrical concern. It generates significant electromagnetic forces within the transformer windings. These sudden, powerful mechanical stresses can be several times greater than those under normal load.
The repeated application of voltage during surge tests (typically three to five times) subjects the transformer's active part—windings, clamping structures, and supports—to repeated mechanical shocks. This process helps to:
  • Check​ the integrity of winding bracing and clamping.
  • Settle​ the core and winding assembly, identifying any loose components that may have shifted during transport or installation.
  • Confirm​ the robust mechanical design and construction of the unit.
This is especially important for large oil transformers​ and power transformers, where mechanical integrity is paramount for a decades-long service life.